8am - Col is at the block
12pm - Col is at the block
4:15pm - Renee is at the block
5pm - Col & Renee are at the block
8:30pm - Col & Renee are at the block
On my way to work I swang past the block, during my lunch break at work i drove past to have a look, after work i had a look, and then went back after the kids were asleep. I'm starting to think the biggest expense of this whole process might be petrol.
At 8am, prior to everything starting the block was pegged out so the guy driving the little thing that lifts dirt and puts it somewhere else
At Midday, while eating my Hungry Jacks lunch and sitting in the car, i watch as he continued to dig out the bottom part of the block.
At 5pm, the bottom part of the block is complete and the top part has had a fair chunk of dirt removed. He estimated it would take a further couple of hours to complete. We overhead our bobcat driver and the one across the road commenting on how horrible the soil (clay) is.
Once the kids were asleep and before it got dark we headed back to the block to see the completed excavation. Its nice to see the block cut and things starting to happen.
We hear that the slab will be down next week, but need to confirm the exact date.